The procure-to-pay cycle at a glance
- Indent (purchase requisition). A site or department asks for material or a service.
- Budget check. Is there budget left for this item, project or cost centre?
- RFQ. A request for quotation goes to several vendors with the specification, quantity, delivery place and date.
- Quotes and comparative statement. Quotes are compared on landed cost: rate, taxes, freight, delivery time and payment terms.
- Approval. The choice is approved under your delegation rules.
- Purchase order. The PO is issued to the selected vendor.
- Goods receipt (GRN). Stores record what actually arrived, its quantity and condition.
- Vendor bill and three-way matching. The bill is matched with the PO and the GRN.
- Payment. The approved amount is paid, with TDS deducted where applicable.
Where money leaks, and the control that stops it
| Leak | Control |
|---|---|
| Buying beyond the budget | Hard budget check before PO release |
| Always buying from the same vendor | Minimum number of quotes per RFQ; recorded comparative statement |
| Paying for goods never received | Three-way matching: PO = GRN = bill |
| Paying a higher rate than agreed | Bill rate locked to PO rate; variance needs approval |
| Duplicate payment | One bill number per vendor per year; payment linked to bill |
| Rates creeping up over time | Price history by item across all projects |
Writing a good RFQ
- Use a clear item description with make or specification, and say whether equivalents are acceptable.
- State the quantity and unit, the delivery address and the date needed.
- Ask for rates with taxes shown separately, plus freight, unloading and validity.
- State payment terms and any penalty for late delivery.
- Give a deadline for quotes.
Three-way matching explained
Before a vendor is paid, three documents must agree:
- Purchase order: what you agreed to buy, at what rate
- Goods receipt note: what actually arrived
- Vendor invoice: what the vendor is charging
If the invoice says 100 bags at ₹420 but the GRN shows 95 bags received and the PO rate was ₹410, the system pays for 95 bags at ₹410 and flags the difference. That single check stops a large share of over-payments.
Automating it
In QuantProc, the whole cycle runs in one system. Sites raise indents on the phone, the PO is blocked if it exceeds the remaining budget, and bills are matched to the PO and GRN before they reach accounts. With QuantProc Sourcing, RFQs go to verified, GST-registered sellers, and the winning quote becomes the PO.
See QuantProc on your own numbers
Book a 30-minute demo. We set it up with your company, your projects and your GST details.
Frequently asked questions
What is the difference between procure-to-pay and source-to-pay?
Procure-to-pay covers buying and paying: requisition, PO, receipt, invoice and payment. Source-to-pay adds the sourcing steps before that, such as finding and evaluating suppliers, RFQs, negotiation and contracts.
How many quotations should an RFQ get?
Many companies require at least three comparable quotes for purchases above a set value, with a recorded reason when fewer are available.
What is a comparative statement?
A comparative statement puts the quotes for an RFQ side by side, item by item, with landed cost and terms, so the approver can see why a vendor was chosen.